Analysis of Proposed Smart Grid Pilot Projects

New Jersey Division of Rate Counsel
Project completed August 2010.

Synapse analyzed two proposed Smart Grid Pilot Projects filed by Rockland Electric Company (RECO) that were awarded Department of Energy Smart Grid Grants. One proposed project would be to install automated distribution equipment in two substations within the RECO service territory. Another proposed project would incorporate distributable back-up battery storage technologies into existing solar photovoltaic systems installed within the RECO service territory. Although both projects were awarded federal stimulus funding that would defray 50% of approved costs, Synapse recommended that the battery storage system pilot project be funded through New Jersey’s Clean Energy Program since the results would benefit all New Jersey ratepayers, not just RECO ratepayers.