New Jersey Division of Rate Counsel
Project completed in 2013

On behalf of the NJ Division of the Ratepayer Advocate, Synapse analyzed the request for cost recovery for expenditures by PSE&G on the Branchburg-Roseland-Hudson transmission line, which was abandoned due to PJM removing the line from its list of needed projects. Synapse analyzed the expenditures in the context of FERC's incentive order allowing for abandonment cost recovery.